Project Details

Project
Plant Room and Internal Pipework Upgrade

Location
Northampton School and Science College

Date
September 2018

After a successful tender process, Ignis were awarded the contract to upgrade the plant room and internal pipework including all fan convectors and radiators throughout the 6th form building.

The existing Atmospheric boilers and flue system was replaced with Energy efficient Remeha Quinta Pro boilers mounted on a pre-fabricated frame complete with manufactures low loss header kit.

New Andrews gas fired water heater, Flues, Mikrofill EFD and Grundfos pumps were also installed to complete the plant room refurbishment.

Our works also included a full upgrade of the BMS control panel installing a new user-friendly control facia. Full demonstration was delivered to staff on site.

Working to a tight deadline our teams ensured hot water was available for school return in September and all internal classroom works were complete